Upgrade of API Production Facilities
| Project Duration: |
August 2006 to December 2006 |
| Project Features: |
API Manufacturing Facility |
| Works Included: |
The provision of specialist Design and Project Management services for the upgrade of fermentation and purification processes. |
Project Outline:
- Synertec provided a Project Management resource to manage the design, construction and validation activities for :
- New process ultra-filtration unit
- Sterilisation systems to fermenter
- Upgrade to fermenter to improve sterility
- The installation and validation of the ultra-filtration works were completed successfully. The fermenter works are ongoing.