Synertec were engaged by Ego Pharmaceuticals to provide process, mechanical, process automation and electrical consulting services for their new flammable manufacturing facility.
The Challenge
Ego Pharmaceuticals required consulting services for their new flammable manufacturing facility, starting from concept design through to detailed design, procurement, installation, commissioning and qualification.
The Project Scope included:
2 x 2000L Topical Liquids & Gels Manufacturing Vessels
Building extension – AS1940 Fire Rated / Hazardous Area / Cleanrooms
Product contact utilities – PW, CA, CIP
Synertec's Solution
Synertec’s engineers and draftsmen executed the process, mechanical, electrical and control elements of the project. Synertec provided procurement and construction support services as well as automation services for PLC coding, SCADA configuration, FAT & SAT.
Synertec’s engineers directed the commissioning activities by piping and electrical contractors and executed the equipment qualification for process & CIP systems, and for product contact utilities.
Synertec’s Scope included:
Process, mechanical, process automation and electrical design
Procurement and construction support for process / product contact utilities
Process automation – coding, configuration, FAT & SAT
Commissioning & qualification – process / product contact utilities